I have a set of Dell 6248 switches. I have a few questions to explore:
1) Can I add/remove CX4 cables while the switch is running? (I assume this is the same rules as a normal Ethernet cable...)
2) Can I add/remove modules while the switch is running?
First scenario I am looking at: extend stack to an unstacked rack.
I'm thinking the process here is, install a spare switch with stacking module, run stack cables back to the stack, breaking and re-assembling the ring, then power the switch up, confirm stack ID and connectivity, and migrate clients over to it. I can totally hot plug the CS4 cables, right?
Next scenario I'm curious about: upgrade stack from 12G to 48G.
Can I swap the 12GB stacking card out and swap the 48G card in while the switch is running or do I need to power off? At the connectors on the 48G card the same? (CX4..) Can I mix/match 48G and 12G cards in a stack during my upgrade process? Is the cable length limit the same (3M) on a 48G stack?
Thanks!
-danny